How India Buys Weapons โ DAP 2020 From AoN to Contract, Step by Step
Every capital acquisition in India follows the Defence Acquisition Procedure (DAP) 2020. Understanding it explains why programmes take a decade โ and where a vendor can actually influence outcomes.
The categories (in order of preference)
- Buy (Indian โ IDDM) โ indigenously designed, developed and manufactured, minimum 50 percent indigenous content.
- Buy (Indian) โ Indian vendor, 50 percent indigenous content (60 percent if not indigenously designed).
- Buy & Make (Indian) โ initial buy from a foreign OEM, then licensed manufacture in India.
- Buy (Global โ Manufacture in India) โ foreign vendor who sets up Indian manufacturing.
- Buy (Global) โ outright import; requires justification that nothing above applies.
Plus Make-I (government-funded development, up to 70 percent), Make-II (industry-funded prototypes with assured orders), Make-III (import substitution), the iDEX and Technology Development Fund routes, and Strategic Partnership for submarines, fighters, helicopters and armoured vehicles.
The ten steps
- Services Qualitative Requirements (SQRs) framed by the user service.
- Acceptance of Necessity (AoN) by the Defence Acquisition Council (DAC) โ the headline "DAC clears โนX crore" news.
- Request for Proposal (RFP) issued to vendors; validity typically 12 months.
- Technical evaluation of bids by a committee.
- Field evaluation trials in summer, winter and high-altitude conditions.
- Staff evaluation and a general staff report.
- Commercial negotiation with the L1 (lowest compliant) bidder.
- Competent financial authority approval โ Defence Minister up to โน2,000 crore, Finance Minister up to โน3,000 crore, Cabinet Committee on Security above that.
- Contract signature.
- Delivery, offsets (for Buy Global above โน2,000 crore) and lifecycle support.
AoN to contract averages three to five years; trials alone commonly take 18 months.
Where programmes stall
- SQRs written around a single product, then challenged by competitors.
- Single-vendor situations after trials, which DAP discourages.
- Cost negotiation with a foreign OEM for licence production.
- Budget: an AoN is not money; the contract needs a line in that year's capital budget.
The 2024-25 revisions
Faster emergency procurement (contracts within six months under delegated powers), higher indigenous content thresholds, a simplified iDEX-to-order pathway, and integrity-pact and offset changes that favour technology transfer over component purchase.
Track live programmes in the procurement tracker.
Tags: DAP 2020, Procurement, DAC, Make in India, Industry. Spotted an error? Request a correction.